Technical Due Diligence (TDD) of power generation facilities in Khmelnytskyi Region, Ukraine

← All projects

Technical consulting engineering services for the Technical Due Diligence (TDD) of the Customer’s power generation facilities in Khmelnytskyi Region, Ukraine. The assignment covered both the completed first-stage 851 kW gas-piston power generation unit and the second-stage development comprising a 4.6 MW gas-piston power unit and a 1.6 MW / 3.2 MWh Battery Energy Storage System (BESS). The assessment focused on the technical condition, design, equipment, infrastructure, implementation status and key risks associated with the facilities.

Our services

  • Assessment of the planned 4.6 MW gas-piston power generation unit;
  • Technical Due Diligence of the 1.6 MW / 3.2 MWh BESS;
  • Review of available design, engineering and technical documentation;
  • Assessment of major equipment, systems and supporting infrastructure;
  • Review of construction and implementation status of the facilities;
  • Assessment of grid connection and utility infrastructure, where applicable;
  • Identification and assessment of key technical and implementation risks;
  • Review of compliance with applicable technical and regulatory requirements;
  • Preparation of Technical Due Diligence Reports with findings, conclusions and recommendations.